Project Atlas

European industrials · Restructuring · Day 62 of 100

PRHVLFMBAKDO
Budget burn£4.2M / £6.1M
+£0.4Mthis fortnight
69% of fees drawn · on plan
Days remaining38
of 100-day plan
Day 62 · final readout Day 100
Open tasks17
-4vs. last week
3 high priority across the team
Deliverables9 of 14
+2accepted by client
5 in review or drafting

Key dates

Upcoming milestones to Day 100

  • Steering committee reviewDay 65 · 18 JunOn track
  • Working-capital deep diveDay 68 · 21 JunAt risk
  • Lender update pack dueDay 72 · 25 JunOn track
  • Footprint options to boardDay 80 · 03 JulScheduled
  • Final value-capture readoutDay 100 · 23 JulScheduled

Recent activity

Across documents, tasks, and reviews

Today
LF

Lena Fischer uploaded Working capital model v6

2h ago
MB

Marcus Bell commented on SKU rationalisation memo

4h ago
PR

Priya Rao approved Lender update pack

6h ago
Earlier
HV

Henrik Vidal reassigned Footprint consultation task

Yesterday
AK

Anna Kim uploaded Logistics tender comparison

Yesterday
DO

David Osei completed 13-week cash flow refresh

2 days ago